Tässä herää kysymys että mitä hiilidioksidille tapahtuu talteen oton jälkeen?
Wärtsilä Gas Solutions, part of technology group Wärtsilä, will supply the cargo handling systems for two very large Ammonia Carrier (VLAC) vessels being built at the Hanwha Ocean shipyard in Korea. The 88,000 m3 capacity vessels have been ordered by a Japanese ship owner. This latest order, which was booked by Wärtsilä in Q2 2025, further strengthens the company’s established leading position as a supplier of cargo handling systems.
The Wärtsilä equipment is scheduled for delivery to the yard commencing in Q4 2025.
Technology group Wärtsilä will supply power generation equipment for a new 30 MW power plant being set up on Victoria Island in Lagos by a Nigerian independent power producer (IPP). Wärtsilä will also operate and maintain the power plant for a period of five years on behalf of the customer. The engineering, procurement, and construction (EPC) responsibility, together with the operation and maintenance (O&M) agreement, has been entrusted to Wärtsilä by Victoria Island Power Ltd. (VIPL), the special purpose company incorporated by Lagos-based Elektron Energy for this project. The equipment supply contract was booked by Wärtsilä in Q4 2024
The facility will comprise three Wärtsilä 34SG gas engine-generator sets with related auxiliaries and is configured to accommodate an extension with one additional engine-generator set at a later stage. The Wärtsilä modular power plant design concept enables this in a cost-effective manner with minimal disruption to ongoing operations.
This project is a first-of-its-kind for Nigeria and is expected to serve as a model to enable similar, optimally sized and locally financed power projects in the country
Technology group Wärtsilä will supply its Wärtsilä 20 main engine and selective catalytic reduction (SCR) system for a new 40.9-metre long state-of-the-art fishing vessel, specifically designed for lobster fishing. The vessel, which will operate in North Atlantic waters, has been ordered by Canadian operator Clearwater Seafoods and will be built at the Hvide Sande Shipyard in Denmark. The order was booked by Wärtsilä in Q2 2025.
The Wärtsilä equipment is scheduled for delivery during the first quarter of 2026.
En tiedä miten Wärtsilän kohdalla toimitaan, mutta vaihtoehtojahan on varastoinnin lisäksi kierrätys polttoaineeksi, lannoitteeks ja mitä nyt hiilestä ylipäätään tehdään.
CCU CCS (carbon capture and utilisation or storage) ovat tärkeitä teknologioita ilmastonmuutoksen hillitsemisessä. Kehitämme ratkaisuja esimerkiksi teollisuuden, liikenteen, maatalouden, energian ja monen muun alan hyödynnettäväksi.
Kemikaaleja, polttoaineita ja materiaaleja voidaan tuottaa ilman fossiilisia luonnonvaroja
En osaa sanoa onko talteenotetun hiilen jatkokäsittely sitten Wärtsilän käsissä, vai hoitaako asiakas hiilenkäsittelyt itse/myy eteenpäin tai ostaa palvelun jostain.
Sen verran uuden äärellä ollaan tässä että olettaisin käsittelyketjujen olevan rakennusvaiheessa vielä.
Danske Bankilla aamukatsaus-analyysiä, luettavissa tänään: Sijoittamisen aamukatsaus
Positiivista sanomaa, Osta-suositus säilyy, tavoitehinta 20 → 22 eur.
Technology group Wärtsilä has expanded its long-term partnership with EDF Renewables UK and Ireland (hereafter EDF Renewables) to accelerate the United Kingdom’s progress toward achieving clean power by 2030. Construction has started on two additional projects, adding to the existing portfolio of six energy storage projects. In total, Wärtsilä will deliver eight sites for EDF Renewables, offering 404.5 MW / 709 MWh of energy storage capacity across the UK. Under the partnership, Wärtsilä recently completed the fifth and sixth grid-scale battery energy storage projects and signed additional long-term service agreements to ensure performance and reliability across all systems.
To date, six out of eight facilities are operational. The projects that recently reached completion include the 50 MW / 100 MWh Sundon project in Bedfordshire, which began commercial operations in December 2024, followed by the 57 MW / 114 MWh Bramford project, located in Suffolk, in April 2025. The two additional projects—Indian Queens in Cornwall and Bredbury in Greater Manchester—are currently under construction. Bredbury (50 MW / 100 MWh) is scheduled for completion by late 2025 and Indian Queens (47.5 MW / 95 MWh) is expected to come online in the first half of 2026.
As more facilities become operational, ensuring optimal system performance becomes critical to business success. All eight projects are covered by Wärtsilä’s long-term service agreements, providing EDF Renewables with increased operational efficiency and cost predictability. The long-term service agreements for the Sundon, Bramford, Indian Queens, and Bredbury projects guarantee performance levels, backed by a dedicated support team.
Alongside Wärtsilä’s battery energy storage systems, all eight sites are managed by Wärtsilä‘s controls and optimisation software, GEMS. GEMS provides EDF Renewables with data-driven insights for comprehensive asset management, performance optimisation, and market trading. It also enables EDF to maximise revenue opportunities through grid services such as electricity market trading and frequency response, while simultaneously bolstering grid stability.
Wärtsilä’s total portfolio with EDF Renewables includes:
Cowley & Kemsley – each 50 MW / 50 MWh
Coventry & Bustleholme – each 50 MW / 100 MWh
Sundon – 50 MW / 100 MWh
Bramford – 57 MW / 114 MWh
Indian Queens – 47.5 MW / 100 MWh
Bredbury – 50 MW / 100 MWh
Wärtsilän hiilidioksin talteenottotekniikka on saanut palstatilaa Tekniikka&Talouden sivuilla. 70 % päästövähennys polttoainetta vaihtamatta on mielestäni hyvä lisä Wärtsilän tarjoomaan päästövähennysteknologioissa.
Tässä on Paulin kommentit Wärtsilän perjantaisesta strategiapuhelusta.
Wärtsilä järjesti perjantaina 6.6. kvartaalittaisen strategiapuhelun, jossa yhtiön toimitusjohtaja Håkan Agnevall kävi läpi yhtiön kannalta keskeisiä teemoja ja vastasi analyytikoiden kysymyksiin. Kokonaisuudessaan näyttäisi, että markkinan kysyntäajurit ovat pääosin ennallaan Q1-raporttiin nähden.
Wärtsilä Gas Solutions, part of technology group Wärtsilä, will supply the cargo handling and fuel supply systems for four new Very Large Gas Carriers (VLGCs) being built in COSCO Shipping (Qidong) Offshore for their owner group. Wärtsilä Gas Solutions’ position as a leading designer and supplier of such systems was cited as a key factor in the award of this contract. The order for two vessels was booked by Wärtsilä Gas Solutions in Q4, 2024, and the order for the additional two vessels in Q2, 2025.
The complete Wärtsilä Gas Solutions’ scope covers the engineering, material, as well as the supervision, commissioning and gas trials for the systems. Included in the materials scope are the machinery, instrumentation, electric and control system. Wärtsilä Gas Solutions will also provide on-site shipyard assistance during the vessels’ construction.
The Wärtsilä Gas Solutions equipment is scheduled for delivery to the yard commencing in the second half of 2025. The four 88,000 cubic meter VLGCs are expected to begin commercial operations from late 2026 onwards.
Wärtsilän sijoittajasuhteissa ollaan tänään siirrytty hiljaiselle kaudelle -IR blogissa tiivistelmä hiljaista kautta edeltävästä puhelusta. Wärtsilässä nämä puhelut ovat kaikille sijoittajille tasapuolisesti avoinna ja tallenteet löytyvät nettisivuiltamme.
Tiivistelmä Q2 2025 hiljaista kautta edeltävästä puhelusta
Technology group Wärtsilä will supply an engineering, procurement, and construction (EPC) extension project to an existing power plant on the Caribbean Island of Aruba. This will add an additional 36 MW of generating capacity, thereby mitigating possible supply shortages due to rapidly increasing demand. Currently Wärtsilä provides 194 MW of generating capacity to Aruba with 4 Engine House power installations. When completed, Wärtsilä’s share of the island’s power generation capacity will be 230 MW, representing 85 percent of the 268 MW total.
The order has been placed by WEB Aruba N.V, the island’s sole water and energy production company. It was booked by Wärtsilä in Q4 2024. The scope includes installation of two Wärtsilä 50DF dual-fuel engines and auxiliaries. Furthermore, based on past experiences, additional features have been designed to optimise overall plant reliability, and to limit existing engine downtime during construction of the extension.
The Wärtsilä engines are scheduled to be delivered in the third quarter of 2025, and the project is expected to be commissioned and fully operational by mid-2026. In carrying out the expansion of the existing plant, existing radiator fields and auxiliaries will need to be relocated as there is limited space in which to install the two additional engines.
Technology group Wärtsilä has signed a five-year Lifecycle Agreement with Greek, Athens-based LNG management company, Alpha Gas. The agreement covers two LNG carriers which each have four Wärtsilä 34DF engines and is aimed at giving Alpha Gas increased operational insight, availability, and better maintenance cost predictability. The order with Wärtsilä was booked in Q2 2025.
In today’s legislative and economic environment, shipowners and operators are increasingly looking for support in maximising efficiency and use of their assets. For LNG carriers in particular, which have limited opportunities for unscheduled stops and downtime, they are specifically looking to safeguard the reliability of their vessels.
Wärtsilä signed a similar agreement with Alpha Gas in November 2024 covering two more LNG carriers. The four Alpha Gas sister vessels now covered by the Wärtsilä Lifecycle Agreement are the Energy Pacific, Energy Endeavour, Energy Integrity, and the Energy Intelligence.
Technology group Wärtsilä will supply a 204 MW power plant solution for the Reko Diq copper-gold mining project in Pakistan. The power plant will operate with 12 Wärtsilä 50 engines and auxiliaries. The order was placed by Reko Diq Mining Company (RDMC) and booked by Wärtsilä in Q2 2025.
The Wärtsilä solution will provide a critically needed reliable and economical power supply, enabling mining operations to function efficiently. Reko Diq is one of the largest undeveloped copper-gold projects in the world, and a globally significant mining initiative. The project site is located in a remote region of Balochistan, Pakistan.
The power plant will be delivered under an engineering, procurement, and construction (EPC) contract, and will include technological provisions to enable the engines to be converted to operate with alternative fuels in the future. In addition to engines, the contract scope includes full heat recovery boilers to support the addition of Flexicycle (Steam Turbine). The plant is designed to integrate renewable energy sources and includes provisions for a future grid connection. The Wärtsilä equipment is scheduled to be delivered commencing in late 2026.
Tässä on Paulin ennakkokommentit, kun Wärre kertoo tuloksestaan perjantaina.
Wärtsilä raportoi Q2-osavuosikatsauksen perjantaina 18.7. klo 8.30. Odotamme yhtiön hyvän tuloskehityksen jatkuvan vahvan tilauskannan tuella. Arvioimme yhtiön jatkavan ohjeistuksessa positiviisella linjalla, sillä USA:n tulliuhittelu ei näyttäisi vaikuttaneen merkittävästi yhtiön suurimpiin liiketoimintasegmentteihin. Pidämme tilauskasvun maltillistumista kuitenkin todennäköisenä suhteessa viimeisen 12kk:n vahvaan 11 %:n tasoon.
Todella iso tilaus (282MW) Jenkeistä.
Tässä on Paulin kommentit Wärren tästä uudesta tilauksesta.
Wärtsilä kertoi ensimmäisestä Yhdysvaltoihin datakeskukseen kohdistuvasta voimalaitostoimituksesta. Emme näe uutisen aiheuttavan merkittäviä konsernitason ennustemuutostarpeita lähivuosille, mutta näemme uuden kasvusegmentin asteittaisen aukeamisen kuitenkin hieman vahvistavan yhtiön pitkän aikavälin kasvuprofiilia. Yhtiö raportoi Q2-osavuosikatsauksensa perjantaina 18.7. jolloin myös tarkastelemme ennusteitamme ja päivitämme näkemystämme viime aikoina merkittävästi noussut osakekurssi huomioiden.
Wärtsilä on sopinut Marine Electrical Systems -yksikkönsä myymisestä VINCI Energies -yhtiölle. VINCI Energies on globaali yhtiö, joka tarjoaa moniteknisiä ratkaisuja ja palveluita energia- ja liikennealoille, viestintäinfrastruktuuriin sekä rakennuksiin, tehtaisiin ja IT-järjestelmiin.
Marine Electrical Systems on pitkissä asiakassuhteissaan erikoistunut laivojen monimutkaisiin sähköjärjestelmäintegrointeihin tuomalla yhteen omat ja telakan lisäämät laitteet yhdeksi sähköverkoksi. Osana Wärtsilä Portfolio-liiketoimintaa Marine Electrical Systems -yksikköä on johdettu itsenäisesti tavoittena tukea Wärtsilän taloudellista tulosta ja vapauttaa yhtiölle arvoa myymällä liiketoiminto. Vuonna 2024 Marine Electrical Systemsin liikevaihto oli 100 miljoonaa euroa. Yksikön myynnissä ostajalle siirtyvät Wärtsilä SAM Electronics GmbH -yhtiö sekä Brasiliassa toteutettava projekti
Kaupan täytäntöönpanon odotetaan toteutuvan vuoden 2025 viimeisen neljänneksen aikana tarvittavat hyväksynnät huomioiden
Tässä on vielä Paulin mielenkiintoiset kommentit Wärren divestoinnista, joka ei sinällään ollut iso juttu.
Suora taloudellinen vaikutus yhtiön arvoon on erittäin vähäinen, mutta lähtökohtaisesti konsernin rakenteen yksinkertaistuminen voidaan nähdä positiivisessa valossa.
Liikevaihto alle Inderesin mutta yli konseksuksen odotusten. Liikevoitto yli ja tilaukset r e i l u s t i yli odotusten.